Friday 17 July 2015

Nelligen Hemp Studio

Photo: Nicole Martin


Location:
Nelligen, NSW South Coast

Type of Build:
Two storey studio on rural block.

Owner:
Nicole Martin

Designer:
Nicole Martin

Builder:
Nicole Martin, Owner Builder

Size :
107m2  total; 63m2 downstairs and 54m2 upstairs loft.

Cost:
Est $200,000

Date of construction:
 April 2012 – est September 2015

Purpose of Build:
An artist’s studio. 

Choice of Material:
Nicole was interested in natural building materials for environmental and health reasons. She also wanted to build the studio herself and wanted the build to be low tech and manageable for an owner builder. Nicole looked into building with straw bales but was worried about vermin and that the width of the walls took up a lot of the floor space. She also looked into building with cob but decided that the material was too heavy to work with on the sloped location. Nicole found hemp through research on natural building techniques, hemp ticked all the boxes. It met the fire regulations, is resistant to termites, lightweight, environmentally responsible, able to be self built and provided a healthy breathable building. 
Nearing completion       Photo: Nicole Martin
Climate:
Zone 6 – Mild Temperate

Local Council:
Eurobodalla Council

Obtaining Approval:
No issue with Council as the build used a regular frame, met the fire code and BASIX, which were the issues that Council was concerned about. Nicole submitted the plans to Council with information about the hemp wall fire resistance and insulation value and no questions were asked about hemp.

Construction:
Nicole carried out the build as owner builder. She worked with a builder on site for 8 weeks to put up the frame, recycled posts and beams,  and the roof and rafters. A crane was brought in to put the large recycled wharf timbers in place. Nicole carried out the remainder of the build herself, except for the plumbing and electrical, with some help from friends and family.

Footings:
The concrete slab is half on ground and half suspended. The suspended slab is supported on a steel reinforced concrete filled concrete block wall on a concrete strip footing on concrete piers. 

Floor:
The ground floor is a concrete slab with ¼ strength black oxide.  The upper storey floor uses recycled  140mm Tasmanian Oak timber from a warehouse in Victoria.

Frame:
Partly large recycled Turpentine wharf timber posts and beams from the CSR factory in Sydney, and partly standard timber frame made off site at Lawmans Frame and Truss in Moruya. The upper floor joists are mixed hardwood from recycled telegraph poles.

Walls:
300mm hemp walls using AHMC (Australian Hemp Masonry Company) binder, with part of the east wall 500mm thick (due to a design change as this wall was originally going to be faced in stone). The walls are finished internally and externally with AHMC hemp lime render, applied in one coat about 10mm thick. No colour was added to the render and it has taken on the colour of the sand.

Under construction
Windows:
Locally made double glazed timber windows and glass doors. The windows have timber sills and storm mouldings ontop attached to the exposed timber lintels. The side window revels are rendered up to the window frame. Internal window reveals are rendered. Fibre cement permanent formwork was installed around the windows and doors.  

Ceiling:
Upstairs Gyprock; downstairs exposed bottom of upstairs recycled Turpentine floorboards.

Roof:
Corrugated Colorbond roofing in Windspray, over foil backed blanket sarking/insulation, with R3.5 sheep’s wool insulation between the rafters.   

Heating:
Nectre wood heater.   

Cooling:
The building uses only natural ventilation with the openable skylights drawing heat out of the house by convection.

Wall construction:
The walls construction was carried out by Nicole with help from friends and family, using a 120L electric pan mixer hired from a friend. Nicole gained experience helping a friend build their hemp walls.

Formwork:
Recycled OSB (oriented strand board). The frame was placed inside the hemp walls but was offset from the centre so that there would be deep window reveals on the inside. The inside walls were 150mm from the frame and the longest bugle batten screws were 150mm. To overcome this Nicole attached blocks of timber to the frame to attach the formwork to. With different sized gaps the use of spacers was awkward and Nicole abandoned them in favour of putting up the formwork using a level to space the formwork. The benefit of this was that there were no spacer holes to fill.
Section Diagram: 


Technical issues:
The offset frame and depth of the wall created issues that were resolved as above. The Gyprock ceiling was time consuming for a novice.The sheet bracing that was required because the building was located in a high wind area, was awkward to place hemp around and on the thin side caused the render to crack.

Advice/Recommendations:
Just do it.
Do not use sheet bracing, if need be find an engineer who can come up with a bracing solution that does not use sheet bracing.

Contact:
Nicole Martin
folkloreandco@outlook.com

11 comments:

  1. This comment has been removed by the author.

    ReplyDelete
  2. Nice labelled representation of colorbond roofing structure which is very light and lost lasting. The other important thing is that it requires less maintenance cost.

    ReplyDelete
  3. Nice write up. If you would like to learn more about Hemp https://www.thcint.com/hemp-history #thcint

    ReplyDelete
  4. This comment has been removed by a blog administrator.

    ReplyDelete
  5. Very informative.....Thanks for sharing information..please update the blog.Non Explosive Demolition Agent

    ReplyDelete
  6. Dabbl is a top manufacturer and distributor company of the large range of Shower Enclosures, Cubicle and Many More. We offer a best quality and design product that fits to any expectation of the Consumer Contact us export4@dabbl.de more details visit here Shower Enclosure, Shower Doors, Shower Cubicle

    ReplyDelete
  7. Great post!!Thanks for sharing it with us....really needed.EXPANDO is the ideal alternative to noisy, risky concrete and rock breaking solutions like explosive blasting, jack hammering, concrete saws and stone cutters - particularly on sites with noise restrictions, vibration issues, safety risks, confined spaces or environmental pollution concerns.Non Explosive Demolition Agent

    ReplyDelete
  8. A mixer is the best way to mix sand and cement rendering a wall. Screed battens fixed to wall to help level render. Use a straight edge to level up render.
    http://renderplus.com.au/service/wall-cladding/

    ReplyDelete
  9. Great you have posted amazing facts.A good construction required the best technical equipment. bpsdevelopments are well known for their great massive building construction.
    If anybody searching for Builders in Sylvania then bpsdevelopments would be the right option for you.They are most reliable builders in Sydney they have a great dedicated team with sound experience.


    ReplyDelete
  10. You really write an appreciable blog. Keep updating such good stuff related home buildings. It seems like you are very experienced in blogging. I would like to know more from your. Here we Executive building group is providing one of the best and top Duplex builders Sydney you can visit us for more information.

    ReplyDelete
  11. I think this is an informative post and it is very useful and knowledgeable. therefore, I would like to thank you for the efforts you have made in writing this article. Singapore rope access

    ReplyDelete