Photo: Nicole Martin |
Location:
Nelligen, NSW
South Coast
Type of Build:
Two storey
studio on rural block.
Owner:
Nicole Martin
Designer:
Nicole Martin
Builder:
Nicole
Martin, Owner Builder
Size :
107m2 total; 63m2 downstairs and 54m2
upstairs loft.
Cost:
Est $200,000
Date of construction:
April 2012 – est September 2015
Purpose of Build:
An artist’s
studio.
Choice of Material:
Nicole was
interested in natural building materials for environmental and health reasons.
She also wanted to build the studio herself and wanted the build to be low tech
and manageable for an owner builder. Nicole looked into building with straw
bales but was worried about vermin and that the width of the walls took up a
lot of the floor space. She also looked into building with cob but decided that
the material was too heavy to work with on the sloped location. Nicole found
hemp through research on natural building techniques, hemp ticked all the boxes.
It met the fire regulations, is resistant to termites, lightweight, environmentally
responsible, able to be self built and provided a healthy breathable building.
Climate:
Zone 6 – Mild
Temperate
Local Council:
Eurobodalla
Council
Obtaining Approval:
No issue with
Council as the build used a regular frame, met the fire code and BASIX, which
were the issues that Council was concerned about. Nicole submitted the plans to
Council with information about the hemp wall fire resistance and insulation
value and no questions were asked about hemp.
Construction:
Nicole
carried out the build as owner builder. She worked with a builder on site for 8
weeks to put up the frame, recycled posts and beams, and the roof and rafters. A crane was brought
in to put the large recycled wharf timbers in place. Nicole carried out the
remainder of the build herself, except for the plumbing and electrical, with some
help from friends and family.
Footings:
The concrete
slab is half on ground and half suspended. The suspended slab is supported on a
steel reinforced concrete filled concrete block wall on a concrete strip
footing on concrete piers.
Floor:
The ground
floor is a concrete slab with ¼ strength black oxide. The upper storey floor uses recycled 140mm Tasmanian Oak timber from a warehouse
in Victoria.
Frame:
Partly large
recycled Turpentine wharf timber posts and beams from the CSR factory in
Sydney, and partly standard timber frame made off site at Lawmans Frame and
Truss in Moruya. The upper floor joists are mixed hardwood from recycled
telegraph poles.
Walls:
300mm hemp
walls using AHMC (Australian Hemp Masonry Company) binder, with part of the
east wall 500mm thick (due to a design change as this wall was originally going
to be faced in stone). The walls are finished internally and externally with
AHMC hemp lime render, applied in one coat about 10mm thick. No colour was
added to the render and it has taken on the colour of the sand.
Windows:
Locally made
double glazed timber windows and glass doors. The windows have timber sills and
storm mouldings ontop attached to the exposed timber lintels. The side window
revels are rendered up to the window frame. Internal window reveals are
rendered. Fibre cement permanent formwork was installed around the windows and
doors.
Ceiling:
Upstairs
Gyprock; downstairs exposed bottom of upstairs recycled Turpentine floorboards.
Roof:
Corrugated
Colorbond roofing in Windspray, over foil backed blanket sarking/insulation,
with R3.5 sheep’s wool insulation between the rafters.
Heating:
Nectre wood
heater.
Cooling:
The building
uses only natural ventilation with the openable skylights drawing heat out of
the house by convection.
Wall construction:
The walls
construction was carried out by Nicole with help from friends and family, using
a 120L electric pan mixer hired from a friend. Nicole gained experience helping
a friend build their hemp walls.
Formwork:
Recycled OSB
(oriented strand board). The frame was placed inside the hemp walls but was
offset from the centre so that there would be deep window reveals on the
inside. The inside walls were 150mm from the frame and the longest bugle batten
screws were 150mm. To overcome this Nicole attached blocks of timber to the
frame to attach the formwork to. With different sized gaps the use of spacers
was awkward and Nicole abandoned them in favour of putting up the formwork
using a level to space the formwork. The benefit of this was that there were no
spacer holes to fill.
Technical issues:
The offset
frame and depth of the wall created issues that were resolved as above. The
Gyprock ceiling was time consuming for a novice.The sheet bracing that was required because the building was located in a high wind area, was awkward to place hemp around and on the thin side caused the render to crack.
Advice/Recommendations:
Just do it.
Do not use sheet bracing, if need be find an engineer who can come up with a bracing solution that does not use sheet bracing.
Do not use sheet bracing, if need be find an engineer who can come up with a bracing solution that does not use sheet bracing.
Contact:
Nicole Martin
folkloreandco@outlook.com
This comment has been removed by the author.
ReplyDeleteNice labelled representation of colorbond roofing structure which is very light and lost lasting. The other important thing is that it requires less maintenance cost.
ReplyDeleteNice write up. If you would like to learn more about Hemp https://www.thcint.com/hemp-history #thcint
ReplyDeleteThis comment has been removed by a blog administrator.
ReplyDeleteVery informative.....Thanks for sharing information..please update the blog.Non Explosive Demolition Agent
ReplyDeleteDabbl is a top manufacturer and distributor company of the large range of Shower Enclosures, Cubicle and Many More. We offer a best quality and design product that fits to any expectation of the Consumer Contact us export4@dabbl.de more details visit here Shower Enclosure, Shower Doors, Shower Cubicle
ReplyDeleteGreat post!!Thanks for sharing it with us....really needed.EXPANDO is the ideal alternative to noisy, risky concrete and rock breaking solutions like explosive blasting, jack hammering, concrete saws and stone cutters - particularly on sites with noise restrictions, vibration issues, safety risks, confined spaces or environmental pollution concerns.Non Explosive Demolition Agent
ReplyDeleteA mixer is the best way to mix sand and cement rendering a wall. Screed battens fixed to wall to help level render. Use a straight edge to level up render.
ReplyDeletehttp://renderplus.com.au/service/wall-cladding/
Great you have posted amazing facts.A good construction required the best technical equipment. bpsdevelopments are well known for their great massive building construction.
ReplyDeleteIf anybody searching for Builders in Sylvania then bpsdevelopments would be the right option for you.They are most reliable builders in Sydney they have a great dedicated team with sound experience.
You really write an appreciable blog. Keep updating such good stuff related home buildings. It seems like you are very experienced in blogging. I would like to know more from your. Here we Executive building group is providing one of the best and top Duplex builders Sydney you can visit us for more information.
ReplyDeleteI think this is an informative post and it is very useful and knowledgeable. therefore, I would like to thank you for the efforts you have made in writing this article. Singapore rope access
ReplyDeleteWindow manufacturer companies specialize in producing a wide range of windows tailored to meet diverse architectural needs. They use advanced technology and high-quality materials to create products that offer durability, energy efficiency, and aesthetic appeal. Window manufacturers ensure that their products comply with industry standards, providing homeowners and businesses with windows that are both functional and stylish, ideal for enhancing any property.
ReplyDelete