Photo: Nathan Devine |
Location:
Culburra
Beach, NSW South Coast
Type of Build:
Single storey
detached residence.
Owner:
Kirstie Wulf and Ben Schueler
Designer:
Kirstie Wulf,
Shelter Building Design
Builder:
Owner builder
Size :
123m2 building, 55m2 decks
Cost:
$210,000
Date of construction:
April 2012 - January
2015
Purpose of Build:
To provide a
comfortable, natural, low energy holiday home with room for guests.
Choice of Material:
Kirstie was
looking into natural building materials suitable for construction by an owner
builder. She was investigating light earth (also known as light clay straw)
when she found an article in Owner Builder magazine on hemp and liked the
materials combination of insulation and thermal mass, the
Climate:
Zone 6 – Mild
Temperate
Local Council:
Shoalhaven
Council
Obtaining Approval:
Although
Shoalhaven Council had not come across hemp walls before the Council did not
have an issue with them, but was quite picky about the wording of the
Engineer’s report on the hemp walls and how it referred to the specific
sections of the BCA. This held up Council approval by a few months. Council
inspectors had no issue with the build during construction.
Construction:
The build was
carried out by Kirstie and Ben as owner builders. The excavation, concrete
slab, frame and frame erection, roof and plumbing and electrical were
contracted out and Kirstie and Ben and generous friends constructed the walls
and the internals and fit out.
Footings:
Waffle Pod concrete
slab on ground.
Floor:
Polished
concrete slab. The slab had 3% onyx oxide added making it a very dark grey. The
top of the slab was lightly ground back to expose the mixed river stone in the
slab in a “salt and pepper” look. Ceramic tiles were used in the bathrooms and
laundry.
Frame:
Made off site
by Truss-T –Frames at Bellambi, near Wollongong. The frame was erected by local
builder, Rob Cheadle.
Walls:
200mm hemp
masonry walls externally, constructed using AHMC binder, cast around a
centrally placed 90mm structural pine frame. 10mm of AHMC hemp/lime render
inside and out. Internal walls Magnesium oxide board finished with
Windows:
Rylock
thermally improved aluminium double glazed sliding doors and windows. Temporary
formwork only used around windows and doors. External window reveals were
rendered and sealed to the window with colour matched Sikaflex. Internally the
Rylock windows came with an attached timber reveal. The revel was sized and the
windows placed so that the render finished flush with the timber window reveal,
avoiding the need for further trim and creating a minimalist look.
Ceiling:
Raked
ceilings using hoop pine plywood, left unfinished with a 9mm black shadowline
between sheets. Higgins sheep’s wool
insulation installed between rafters, R3.5 in kitchen/living/dining room and R3
in bedrooms and bathroom. Air cell R1.5 combined sarking, reflective foil and
insulation installed on top of rafters under roof sheeting.
Colorbond
custom orb (corrugated profile) in shale grey.
Heating:
A gas bayonette has been installed but due to
the house’s solar passive design and good insulation, to date the house has not
required any heating in winter.
Cooling:
Natural
ventilation only. Doors and windows were placed to catch summer afternoon sea
breezes and are left open on summer nights to cool down the thermal mass in the
concrete slab.
Wall construction:
Kirstie
attended a hemp building workshop with Klara Maroszekky from the AHMC and a
workshop with Steve Allin (from Ireland) prior to commencing the build. The
workshops both focussed on the mixing and placing of the hemp material, but
lacked information on construction detailing to be used with hemp walls.
Formwork:
OSB (oriented
strand board) recycled from large packing crates, was used as formwork. The
formwork was temporarily attached to the frame with coach bolts and spacers
made from rigid conduit. The spacer holes were filled with hemp mix after the
formwork was removed.
Hemping up
under the rafters was awkward but not impossible. Challenges were also faced
with placing formwork and hemp in to small spaces, particularly in an area
between two roofs. The frame had been constructed without any direction to the
frame builders apart from the specification of 600mm centres for the studs. In
a number of locations the presence of triple studs, particularly next to doors,
meant that the hemp had nothing to key into and in some spots it pulled away
from the frame as it dried. This was resolved by placing crews with large
plastic washers through the wall into the frame pulling the hemp wall back to
the frame. Dealing with long and thick lintels over large windows also posed
some challenges, which with hindsight could have been avoided by using
permanent formwork, but such a decision needed to have been made prior to the
manufacture of the frame to allow for the extra thickness in the openings of the
permanent formwork. Difficulties were also experienced with the application of
the render, particularly on the MgO board.
Advice/Recommendations:
In the design
of the house the ease and ability to make the hemp walls needs to be taken into
consideration. Similarly the house frame needs to be designed to work with the
need for the hemp walls to key in around the frame. It is recommended to test
several renders and colours before committing to a particular render.
Contact:
Kirstie Wulf
Pretty good post. I just stumbled upon your blog and wanted to say that I have really enjoyed reading your blog posts.
ReplyDeleteEntry Door With Sidelights
Windows And Doors Las Vegas
Window Installation Service
Great post!!Thanks for sharing it with us....really needed. EXPANDO is an expansive mortar chemical that cracks rocks and concrete. It is a concrete cutting, granite breaking and general demolition solution...Rock & Concret Breaking
ReplyDeleteI am grateful for this blog to distribute knowledge about this significant topic about beach hemp house. If you want to know more information, Gordon Rutty is best choice.
ReplyDelete