Rear view of studio |
Location:
Kyneton,
Victoria
Type of Build:
Two storey
studio in heritage listed area, attached to rear of existing building.
Owner:
Joe and Deb
D’Alo
Designer:
Ian Murray,
Joe D’Alo and Deborah Varney
Builder:
Joe D’Alo
Size :
67.5m2 total; 40.5m2 downstairs and
27m2 upstairs.
Cost:
$165,000
Date of construction:
January 2012
to lock up stage in 4 months. As a July
2014, still not finished, will need a further 2 months to complete
Purpose of Build:
To provide
separate guest accommodation to be used as a Bed and Breakfast. A unique experience for guests to stay in a
hemp cottage.
Choice of Material:
Joe and Deb
had been following the development of hemp construction for about 15 years.
They have an interest in natural building and Joe had worked on both rammed
earth and strawbale buildings. He saw the flaws with each of these construction
types, such as the thickness of the walls for a strawbale building. Joe saw
hemp construction as addressing some of the disadvantages of these other
natural building methods, so with hemp also providing a combination of thermal
mass and insulation, the choice of hemp for his own build was obvious. Hemp is
an ideal building material for the climate in the region, as it has good
thermal insulation whilst still providing some thermal mass for energy storage.
Climate:
Zone 7 – Cool
Temperate
Local Council:
Macedon
Ranges Council
Obtaining Approval:
Council
approval was granted for this build in a heritage area. A private
certifier/building surveyor was used and there were no particular issues with
the hemp construction.
Construction:
The whole
build was carried out by Joe D’Alo who is a licensed builder. A carpenter with
concrete formwork experience was employed. There was also a team for the
hemp-lime mixing, filling the formwork and tamping.
Footings:
Concrete slab
on ground. Concrete slab is a thickened edge raft slab with internal beams and
expanded polystyrene edge insulation.
Floor:
The ground
floor is tiles over concrete slab. Upper
storey – Alpaca carpet in bedroom and tiled bathroom.
Frame:
Joe made the
timber frame on site.
Walls:
Joe made the
timber frame on site, using Australian Hemp Masonry Company (AHMC) binder, cast
around 90mm structural pine frame. Internal walls were finished with a first
coat of AHMC Binder and sand and a second coat of Plastalite lime/gypsum
plaster. External walls were clad with Spruce Thermowood, which was left to
naturally grey. For the external walls 25mm timber battens were fixed over the
10mm permanent magnesium oxide (MgO) boarding then clad with Spruce Thermowood
weatherboards. The 25mm gap between the
MgO board and cladding creates an insulating layer.
Windows:
Double hung,
double glazed timber windows. Permanent formwork was installed around the
windows and doors.
Ceiling:
The exposed 20mm
Supaboard Magnesium Oxide board floor of the upper storey acts as the ceiling
to the ground floor. Upper storey
ceiling is 10mm Supaboard Magnesium Oxide board which was stopped and finished
in a similar fashion as standard gyprock plaster then painted with a breathable
paint. 250mm of “light hemp” (hemp wall material with less binder and no sand)
was cast over the Magnesium oxide board as ceiling insulation.
Roof:
Corrugated
galvanised metal sheet roofing is used.
Heating:
A wood heater is planned to be used in an old
fireplace, but Joe and Deb have found that the building stays warm in winter
without heating.
Cooling:
The building uses
only natural ventilation. Joe and Deb found that on a 40o C day the
downstairs of the studio stayed a much more comfortable 25 – 26o C.
Wall construction:
Joe is a
licensed builder and carried out the wall construction himself, using a 360
litre diesel pan mixer hired from AHMC. Prior to construction Joe attended a
Hempcrete workshop in Maleney, Queensland, but found the course lacked detail
particularly when it came to how to specifically deal with window and door
openings.
Formwork:
Magnesium
oxide board was used as a permanent formwork on the external side of the wall. Formply
was used for the internal formwork and rather than being attached to the frame
it was braced against a timber stud on the floor so that there were no holes in
the hemp wall.
Section Diagram:
Section Diagram:
Hemping
between the exposed upper floor joists was difficult. The 35o ceiling
was fine to work with but the 47o ceiling was too steep and was
awkward to build. Joe recommends that those interested in hemp building need to
think about how to deal with window and door opening, in terms of lintels,
flashing and how the render is to join the timber (window or door) frames.
Advice/Recommendations:
Joe found
that using an external cladding and permanent formwork on one side of the hemp
wall made the walls quick and easy to go up, because you only have to raise the
formwork on one side, rather than both. Although
Formply was used as the formwork board, ply or OSB would have been quite
suitable and cheaper. The external cladding was also advantageous from the
point that the timber weatherboard cladding used maintained the look of the
other outbuildings. A rendered wall may
have looked out of place.
Joe recommends
runing electricals through conduit through the hemp walls. The mixing and
tamping of the hemp-lime material is initially fun and therapeutic, however things
can quickly change and the process can become a long and arduous task which
will test people’s spirit. A large,
trained team might cost more in direct labour but the benefit will be in
getting the hemp walls constructed quicker thus allowing them to dry (up to 6
weeks) before rendering. The timing may
be of particular importance if seasonal weather conditions are extreme. Hemp lime building shouldn’t be undertaken
when seasonal conditions are extreme, i.e., frost.
Contact:
Joe D’Alo
joe.dalo@bigpond.com
Good read, It really is incredibly fantastic and informative website. Good to discover your site Very well article! keep sharing.
ReplyDeleteFrench Entry Doors
Windows And Doors Las Vegas
Window Installation Service
Contemporary Entry Doors